T&M records that get you paid: a daily routine for restoration crews
Most payment disputes on large losses come down to documentation. A simple daily time-and-materials routine that holds up when the invoice is reviewed.
Ask any restoration contractor about slow pay on a large loss, and you'll hear the same story. The work was done. The crews were there. But when the invoice was reviewed, the records didn't line up, and every question added weeks.
Time-and-materials (T&M) work is where this hurts most, because the invoice is only as strong as the daily record behind it. Here is a routine that holds up.
The rule: record it the day it happens
The single biggest improvement most crews can make is to stop rebuilding records at the end of the job. Memory fades, notes go missing, and reconstructed hours look reconstructed.
Record every day, on the day, and send it the same day.
What goes on the daily sheet
Labor. Every worker on site, with their name, role, time in and time out, and breaks. Note which area of the building each crew worked in.
Equipment. Every piece placed or removed that day, by type and, where you have it, by asset or serial number. Equipment billed by the day needs a clear start date and end date for each unit.
Materials. What was used and where, with receipts attached for anything purchased.
Work performed. A plain-language line or two per area: what was done today and what's planned for tomorrow.
Photos that tell the story
Photos are the evidence behind the sheet. Take them before, during and after, and tie each one to a room, unit or area. A photo with no location is a photo someone has to ask about.
Keep the same angles from day to day where you can. A sequence of photos from one spot shows progress far better than a pile of random shots.
Moisture readings, the same way every day
For mitigation work, take readings at the same marked points every day, with the same meter, and record them alongside the date and the area. Consistent readings are what show a structure drying, and what justify keeping equipment on site.
Get the daily sign-off
Where the property's representative is on site, ask them to review and acknowledge the daily sheet. It takes two minutes, and it turns tomorrow's dispute into today's conversation. Questions raised the same day are easy to answer. Questions raised six weeks later are not.
Reconcile as you go
Once a week, compare the daily sheets against the estimate or the not-to-exceed figure. If you are heading over, say so early, in writing, with the records that explain why. What can be billed is set by your contract, and nobody likes a surprise at closeout.